
Project scope
Project scope
This ongoing project replaces the aging two-battery bank in the starboard engine room that supplies the windlass, aft toilet and sanitation system, and aft shower box. The first phase uses a Victron lithium battery, a lithium-compatible plug-in charger, a fuse, and a smart shunt for monitoring. Future work will refine the charging arrangement and identify several existing cables whose purposes are not yet known.
Tasks completed
Tasks completed
Updates are listed with the newest work at the top.
Latest completed task
Removed the old batteries from the boat
After confirming that the new lithium battery was operating the connected equipment properly, I removed the two old batteries from Hunky Dory and took them home.
Earlier task
Confirmed improved toilet operation
The aft toilet has continued to work very well with the new battery. It flushes noticeably faster and more strongly than it did with the old battery bank.
Earlier task
Installed and tested the lithium battery
I installed the new Victron lithium battery in the starboard engine room and connected the windlass, aft toilet and sanitation system, and aft shower box. One of the old batteries measured approximately 13 volts, while the other measured only 8.6 volts. The failed battery had apparently been pulling down the entire bank and causing the aft toilet to operate slowly.
Two unidentified negative cables were connected to the old bank. I reconnected them during this first-phase installation, but they still need to be traced and identified.
I tested the aft toilet and confirmed that it flushed much better. I also tested the windlass at the dock by retrieving the anchor from the dock and seating it in the bow pulpit. The windlass operated properly while I recorded the smart-shunt readings.
Earlier task
Load-tested the battery and charger
Before installing the battery aboard Hunky Dory, I connected a small inverter and operated a 200-watt space heater as a test load. I reduced the battery from a full charge to approximately 70 percent, then recharged it with the charger set to 25 amps. It returned to a full charge in approximately two hours.
Earlier task
Assembled and tested the charging and monitoring components
I set up the new battery at home and charged it fully with the plug-in charger. The charger progressed through its charging stages and finished in storage mode.
I also fabricated the necessary cables and installed a fuse for the charger, a smart shunt for battery monitoring, and a temporary 12-volt and USB outlet for testing loads.
Earlier task
Traced the existing windlass cabling
I investigated the existing windlass wiring and found that the cable passes through terminal connections below the windlass inside the anchor rode locker. From there, it connects to a larger 1/0 welding cable that runs back to the starboard engine room.
Tracing this cable helped confirm how the windlass was connected to the existing battery bank and where the replacement battery could be installed. I also gathered the parts needed for the initial installation.
Earlier task
Evaluated the original battery bank
The existing starboard battery bank had been powering the windlass and aft sanitation equipment for several years. The aft toilet had begun operating slowly and sometimes would not flush, even after the bank had been connected to its charger.
I recorded the battery brands and model information and began planning a lithium replacement with improved monitoring and charging.
Lessons learned
Lessons learned
- Two batteries connected together can make it difficult to recognize that one has failed. One battery still showed normal voltage while the other had fallen to 8.6 volts.
- Slow operation of the aft toilet was an early indication that the battery bank was not supplying adequate voltage.
- Tracing the existing cable route before installation helped confirm that the windlass could continue using the large cable already running to the starboard engine room.
- Bench-testing the battery, charger, smart shunt, and test load made it possible to verify the basic system before installing it aboard the boat.
- An older boat may have unidentified cables connected to a battery bank. Those cables should be traced before the original system is permanently removed.
- Dividing the project into phases allowed me to restore reliable operation while continuing to plan a more permanent charging arrangement.
Tips
Tips
- Test each battery individually when troubleshooting a multi-battery bank.
- Trace and label every cable before disconnecting the original batteries.
- Use properly sized marine cable, terminals, fuses, and battery switches for high-current equipment such as a windlass.
- Make sure the charger and its settings are compatible with the lithium battery.
- Route every charging source and load through the smart shunt correctly so its state-of-charge readings remain accurate.
- Test the new system with smaller controlled loads before operating the windlass.
- Secure the battery and protect its terminals before operating the boat.
- Follow the battery, charger, and windlass manufacturers’ instructions and applicable ABYC electrical standards when completing the permanent installation.
Related content
Learn more
Restoration projects
How-tos
Project updates
- Pre-testing the Solar Panel SystemSee how panel angle, partial shading, electrical loads, and charging state affected a temporary solar-panel test system.
- Clearing the Way for a New Pilothouse CounterRead about removing the chart cabinet and electronics in preparation for the new mahogany-veneer counter.
Life on board
Cruising
- A Cruise Around Middle Bay LighthouseCruise into Mobile Bay for a close look at the historic lighthouse, an unexpected hat-recovery drill, and dolphins on the ride home.
- Watching the Total Solar Eclipse from Hunky DorySpend eclipse day aboard Hunky Dory, from an early electrical repair to totality and an overnight stay in Demumbers Bay.
- Cruising from Mobile to Demopolis, AlabamaTravel north from Mobile through the Tensaw anchorage, Sunflower Bend, Coffeeville Lock, Bobby’s Fish Camp, and on to Demopolis.
- A Virtual Cruise During LockdownJoin the 2020 Facebook cruise from Lake Barkley to Kentucky Lake and tour Hunky Dory along the way.
